About Dutypoint

Ellesmere Port Lorry Park

Author Lloyd Preston Calendar 2 July 2023

Wastewater pumping solution for industrial lorry park

Delivering outstanding solutions

PROJECT BACKGROUND

Industry sector Transport
Project type Industrial Lorry Park

PROJECT SUMMARY

Formula Truckstop is a premier industrial lorry park in North West England, boasting 120 secure overnight parking bays and outstanding facilities for a comfortable stay.

Our specialists at Dutypoint were appointed to this large-scale project involving installing wastewater pumping station equipment into concrete chambers to ensure the facilities, including toilets, sinks and showers, are clear of wastewater and safe and sanitary for customer use.

PROJECT CHALLENGE

The role our team played at Formula Truckstop lorry park was highly important. No design plan was provided, so our specialists completed a full design of the systems, ensuring we could deliver an efficiently working pump station.

During the installation of the system, our team was imposed with several challenges, with very high surface runoff from the attenuation lake and lorry car park, in addition to the very high flow rates mixed with tight time scales.

PROJECT SOLUTION

Our team persevered and overcame the challenges faced, meeting our client’s needs and hitting tight deadlines.

Our specialists used 200 mm ABS Sulzer XFP Heavy-Duty Wastewater Pumps. These heavy-duty commercial wastewater pumps are EX-rated and designed for heavy wastewater applications in larger commercial applications, such as lorry parks on this site.

The customer was incredibly impressed with the service experience, having received a cracking pump station built to high specification, complete with high-quality pumps, ultrasonic level control and an off-site built baffle plate.

For advice and to ensure your systems are wastewater-free, contact our team today for a solution.

Products used

  • 200mm ABS Sulzer XFP Heavy-Duty Wastewater Pumps
ABS Pump Installed Underground