PROJECT CHALLENGE
Five strategically placed sewage pump stations were required around the perimeter of the building to keep the sewage waste alleviated to a certain level. The build program for this project was very tight and carried numerous challenges.
The rising main lengths varied from 200m to 600m due to the size of the building and had to be carefully selected to ensure the velocity was calculated correctly to keep the pumps running to maximum efficiency.
PROJECT SOLUTION
Dutypoint designed a complete foul-water pump station package to meet the demands of the entire facility. The system included 5 pre-built packaged pumping stations, pumps and 5 rising mains which were all selected specifically for the project.
The system was pre-built off-site and delivered within a specific time window to allow the build program to progress smoothly. Dutypoint also assisted in reducing installation times to get the job on site done quicker and cut out any disruption to other contractors.