PROJECT CHALLENGE
As COVID cases on the island continued to grow, Jersey General Hospital was growing increasingly concerned about the capacity that the facility could take. From the start of the project to full operation, a timescale was given of a month. Dutypoint had to work closely with the client who were coordinating many other companies from different industries to put the hospital together.
As the project was a temporary hospital, solutions needed to be developed from first principles, including patient services to fire strategy. As a healthcare environment, there are specific standards that must be met for heating, cooling and water control. All standards and requirements still had to be met despite the short timeframe.
PROJECT SOLUTION
The Dutypoint team were approached to design and supply a packaged cold water booster system. The system would provide the hospital with domestic cold water and Category 5 water supply.
As the project was during the pandemic, we were experiencing issues of our own, including staff isolation, suppliers being closed, social distancing/government guidelines and general requirements for safe working. Despite this, we still managed to turn around the design, manufacture and delivery of this system within 3 weeks to Jersey. It was a challenge but our team united to achieve the same goal and we succeeded.
Product Offering
- 40′ long x 8′ wide x 8′ 6” high package plant room incorporating:
- 28,000 L storage domestic cold water tank
- 375 L Cat 5 Storage Tank
- VT3-10-030T 3 pump booster set
- WX2-9040-375 2 pump Cat 5 booster set