PROJECT CHALLENGE
Dutypoint were brought into this project at a late stage by a main contractor. The build program was well under way and progressing quickly.
The structural design was completed based on a 1000mm pump chamber but pump flow rates were still in question so orders couldn’t be placed and the specified supplier was quoting 6-8 weeks for delivery.
PROJECT SOLUTION
Dutypoint stepped in and committed to hit a very tight deadline and supplied 2 packaged pump stations for foul and storm water which were customised to suit site requirements and prevent any design structural design amends.
These were accelerated through our design process, manufactured and delivered to site within 3 working days or receiving the order!
What’s more, our packaged pump stations solution was quicker to install, more cost effective and most importantly, safer to install than alternative systems!