PROJECT CHALLENGE
Dutypoint were brought on to this project very late, and due to restrictions on discharge rates still being worked through with Thames Water, the programme became very tight. Dutypoint worked to a very tight and challenging schedule to successfully deliver the pre-packaged pump system within just a few days of receiving the order.
Working closely with McLaren Construction, Dutypoint needed to conform with particularly stringent flow restrictions imposed by Thames Water.
PROJECT SOLUTION
The pre-packaged pump station developed by Dutypoint provided a bespoke solution to exceed the requirements of the client and was delivered on time to a site with extremely restricted access, causing very little disruption to the build project.